A 3 m thick clay layer is subjected to an initial uniform pore pressure of 145 kPa as shown in the figure.
For the given ground conditions, the time (in days, rounded to the nearest integer) required for 90% consolidation would be _______.

Correct : 1770

Similar Questions

Group I lists the type of gain or loss of strength in soils. Group II lists the property or process responsible for the loss or gain of strength in soils. T...
#207 MCQ
A soil sample is subjected to a hydrostatic pressure, ฯƒ. The Mohr circle for any point in the soil sample would be
#208 MCQ
A strip footing is resting on the ground surface of a pure clay bed having an undrained cohesion Cu. The ultimate bearing capacity of the footing is equal to