Civil Engineering > GATE 2016 SET-2 > CPM/PERT
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. The critical duration for this construction project is
A
13 days
B
14 days
C
15 days
D
16 days

Correct : c

Similar Questions

The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P....
#1211 Fill in the Blanks
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding...
#1247 MCQ
In the context of construction project management, which of the following statements is/are true:
#1722 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......