Civil Engineering > GATE 2016 SET-2 > CPM/PERT
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
A
25 and 1
B
1 and 1
C
0 and 0
D
81 and 0

Correct : c