Civil Engineering > GATE 2016 SET-1 > CPM/PERT
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.
The expected completion time (in days) of the project is

Correct : 37