Civil Engineering > GATE 2015 SET-1 > Concrete Technology
Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:
(i) As the slump increases, the Vebe time increases.
(ii) As the slump increases, the compaction factor increases.
Which of the following is TRUE?
A
Both (i) and (ii) are TRUE
B
Both (i) and (ii) are FALSE
C
(i) is TRUE and (ii) is FALSE
D
(i) is FALSE and (ii) is TRUE

Correct : (i) is false and (ii) is true

Similar Questions

The characteristic compressive strength of concrete required in a project is 25 MPa and the standard deviation in the observed compressive strength expected at...
#552 Fill in the Blanks
In the context of provisions relating to durability of concrete, consider the following assertions: Assertion (1): As per IS 456-2000, air entrainment to the e...
#562 MCQ
Concrete of characteristic strength 30 MPa is required. If 40 specimens of concrete cubes are to be tested, the minimum number of specimens having at least 30 M...
#906 MCQ

Related Topics

workability concrete slump measurement compaction factor Vebe time civil engineering gate 2015 civil engineering basics concrete workability GATE civil engineering 2015 concrete compaction factor

Unique Visitor Count

Total Unique Visitors

Loading......