Civil Engineering > GATE 2014 SET-1 > Seepage Analysis
The flow net constructed for the dam is shown in the figure below. Taking the coefficient of permeability as 3.8 x 10-6 m/s, the quantity of flow (in cm3/s) under the dam per meter of dam is _______.

Correct : 7.6