Civil Engineering > GATE 2014 SET-1 > Hydrographs
In reservoirs with an uncontrolled spillway, the peak of the plotted outflow hydrograph
A
lies outside the plotted inflow hydrograph
B
lies on the recession limb of the plotted inflow hydrograph
C
lies on the peak of the inflow hydrograph
D
is higher than the peak of the plotted inflow hydrograph

Correct : b