Chemical Engineering > GATE 2025 > Cost Estimation
The capital cost (CC) of an industrial equipment varies with its capacity (S) as CC ∝ Sβ. The rule-of-thumb value of the exponent β is
A
0.4
B
0.6
C
0.8
D
1.0

Explanation

Correct : b