Chemical Engineering > GATE 2024 > Data Interpretation
The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).
The Capacity Factor of a power generation technology is:
Capacity Factor= Electricity Generation (MWh)/ Installed Capacity (MW) ร— 1000 (h)
Which one of the given technologies has the highest Capacity Factor?
A
T1
B
T2
C
T3
D
T4

Correct : d

Similar Questions

n the given diagram, teachers are represented in the triangle, researchers in the circle and administrators in the rectangle. Out of the total number of the peo...
#295 MCQ
In a detailed study of annual crow births in India, it was found that there was relatively no growth during the period 2002 to 2004 and a sudden spike from 20...
#527 MCQ
The profit shares of two companies P and Q are shown in the figure. If the two companies have invested a fixed and equal amount every year, then the ratio of th...
#728 MCQ

Related Topics

power generation capacity factor T1 T2 T3 T4 comparison chemical engineering GATE 2024 capacity factor calculation electricity generation vs installed capacity chemical engineering GATE power generation technologies highest capacity factor

Unique Visitor Count

Total Unique Visitors

Loading......