Chemical Engineering > GATE 2021 > Cost Estimation
Operating labor requirements L in the chemical process industry is described in terms of the plant capacity C (kg day-1) over a wide range (103-106) by a power law relationship L=αCβ where α and β are constants. It is known that
L is 60 when C is 2×104
L is 70 when C is 6×104
The value of L when C is 105 kg day-1 is _______ (round off to nearest integer).

Correct : 75

Similar Questions

In the year 2005, the cost of a shell and tube heat exchanger with 68 m2 heat transfer area was Rs. 12.6 Lakh. Chemical Engineering Index for cost in 2005 was...
#554 MCQ
The capital cost (CC) of an industrial equipment varies with its capacity (S) as CC ∝ Sβ. The rule-of-thumb value of the exponent β is
#608 MCQ
The purchase cost of a heat exchanger of 20 m2 area was Rs. 500000 in 2006. What will be the estimated cost (in Rs. to the nearest integer) of a similar heat ex...