Chemical Engineering > GATE 2012 > Project Evaluation
Heat integration is planned in a process plant at an investment Rs. 2×106. This would result in a net energy savings of 20 GJ per year. If the nominal rate of interest is 15% and the plant life is 3 years, then the breakeven cost of energy, in Rs. per GJ (adjusted to the nearest hundred), is
A
33500
B
43800
C
54200
D
65400

Correct : b