A batch reactor produces 1×105 kg of a product per year. The total batch time (in hours) of the reactor is k√PB, where PB is the product per batch in kg and k=1.0 h/√kg. The operating cost of the reactor is Rs. 400/h. The total annual fixed charges are Rs. 340×PB and the annual raw material cost is Rs. 2×106. The optimum size (in kg) of each batch (adjusted to the nearest integer) is
Correct : c
Similar Questions
The cost of two independent process variables f1 and f2 affects the total cost CT (in lakhs of rupees) of the process as per the following function: CT = 1000/(...
The Annual Fixed Charges (AFC) and Annual Utilities Costs (AUC) of a distillation
column being designed are expressed in terms of the reflux ratio (R) as...
A person is drowning in sea at location R and the lifeguard is standing at location P. The
beach boundary is straight and horizontal, as shown in the figure....