Chemical Engineering > GATE 2011 > Work and Time
A transporter receives the same number of orders each day. Currently, he has some pending orders (backlog) to be shipped. If he uses 7 trucks, then at the end of the 4th day he can clear all the orders. Alternatively, if he uses only 3 trucks, then all the orders are cleared at the end of the 10th day. What is the minimum number of trucks required so that there will be no pending order at the end of the 5th day?
A
4
B
5
C
6
D
7

Correct : c

Similar Questions

Pipes P and Q can fill a storage tank in full with water in 10 and 6 minutes, respectively. Pipe R draws the water out from the storage tank at a rate of 34...
#161 MCQ
5 skilled workers can build a wall in 20 days: 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team h...
#1107 MCQ
Inhaling the smoke from a burning _________ could _________ you quickly.
#2 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......