Chemical Engineering > GATE 2011 > Cost Estimation
A continuous fractionator system is being designed. The following cost figures are estimated for a reflux ratio of 1.4.
Fixed cost including all accessories (Rs.) forOperating cost (Rs./year) for
columncondenserreboilercondenser cooling waterreboiler heating steam
6×1062×1064×1068×1061×106

The annualised fixed charge is 15% of the fixed cost. The total annualised cost (in Rs.) is
A
10.8×106
B
13.35×106
C
15.9×106
D
3.15×106

Correct : b

Similar Questions

In the year 2005, the cost of a shell and tube heat exchanger with 68 m2 heat transfer area was Rs. 12.6 Lakh. Chemical Engineering Index for cost in 2005 was...
#554 MCQ
The capital cost (CC) of an industrial equipment varies with its capacity (S) as CC ∝ Sβ. The rule-of-thumb value of the exponent β is
#608 MCQ
Operating labor requirements L in the chemical process industry is described in terms of the plant capacity C (kg day-1) over a wide range (103-106) by a power...
#717 Fill in the Blanks

Related Topics

continuous fractionator system GATE Chemical Engineering 2011 annualised fixed charge total annualised cost chemical engineering gate cost of fractionator system fractionator system design GATE 2011 chemical engineering

Unique Visitor Count

Total Unique Visitors

Loading......