Chemical Engineering > GATE 2011 > Cost Estimation
A continuous fractionator system is being designed. The following cost figures are estimated for a reflux ratio of 1.4.
The annualised fixed charge is 15% of the fixed cost. The total annualised cost (in Rs.) is
| Fixed cost including all accessories (Rs.) for | Operating cost (Rs./year) for | |||
|---|---|---|---|---|
| column | condenser | reboiler | condenser cooling water | reboiler heating steam |
| 6×106 | 2×106 | 4×106 | 8×106 | 1×106 |
The annualised fixed charge is 15% of the fixed cost. The total annualised cost (in Rs.) is
Correct : b
Similar Questions
In the year 2005, the cost of a shell and tube heat exchanger with 68 m2 heat transfer area
was Rs. 12.6 Lakh. Chemical Engineering Index for cost in 2005 was...
The capital cost (CC) of an industrial equipment varies with its capacity (S) as CC ∝ Sβ. The rule-of-thumb value of the exponent β is
Operating labor requirements L in the chemical process industry is described in terms of the plant capacity C (kg day-1) over a wide range (103-106) by a power...