A continuous fractionator system is being designed. The following cost figures are estimated for a reflux ratio of 1.4.
Fixed cost including all accessories (Rs.) forOperating cost (Rs./year) for
columncondenserreboilercondenser cooling waterreboiler heating steam
6×1062×1064×1068×1061×106

The annualised fixed charge is 15% of the fixed cost. The total annualised cost (in Rs.) is
A
10.8×106
B
13.35×106
C
15.9×106
D
3.15×106

Correct : b

Similar Questions

In the year 2005, the cost of a shell and tube heat exchanger with 68 m2 heat transfer area was Rs. 12.6 Lakh. Chemical Engineering Index for cost in 2005 was...
#554 MCQ
The capital cost (CC) of an industrial equipment varies with its capacity (S) as CC ∝ Sβ. The rule-of-thumb value of the exponent β is
#608 MCQ
Operating labor requirements L in the chemical process industry is described in terms of the plant capacity C (kg day-1) over a wide range (103-106) by a power...
#717 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......