A plant produces phenol. The variable cost in rupees per tonne of phenol is related to the plant capacity P (in tonnes/day) as 45000+5P. The fixed charges are Rs. 100,000 per day. The selling price of phenol is Rs. 50,000 per tonne.
The optimal plant capacity (in tonnes per day) for minimum cost per tonne of phenol, is
A
101
B
141
C
283
D
422

Correct : b

Similar Questions

The cost of two independent process variables f1 and f2 affects the total cost CT (in lakhs of rupees) of the process as per the following function: CT = 1000/(...
#521 NAT
The Annual Fixed Charges (AFC) and Annual Utilities Costs (AUC) of a distillation column being designed are expressed in terms of the reflux ratio (R) as...
#540 MCQ
A person is drowning in sea at location R and the lifeguard is standing at location P. The beach boundary is straight and horizontal, as shown in the figure....
#557 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......