Biomedical Engineering > GATE 2024 > Quantitative Ability
The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).
Installed Capacity X Electricity Generation. The Capacity Factor of a power generation technology is:
Capacity Factor = Electricity Generation (MWh) / Installed Capacity (MW) x 1000 (h).
Which one of the given technologies has the highest Capacity Factor?

Capacity Factor = Electricity Generation (MWh) / Installed Capacity (MW) x 1000 (h).
Which one of the given technologies has the highest Capacity Factor?
Correct : d
Similar Questions
In a locality, the houses are numbered in the following way: The house-numbers on one side of a road are consecutive odd integers starting from 301, while the h...
For positive integers p and q, p/q≠1,(p/q)(p/q)=p((p/q)-1). Then
Which one of the given options is a possible value of x in the following sequence? 3, 7, 15, x, 63, 127, 255
Total Unique Visitors
Loading......