Agricultural Engineering > GATE 2021 > Size Reduction
In a size reduction operation, the power required to crush 2 ton of feed material per hour is 7.2 kW. Eighty per cent of the feed and product material pass through 4.75 mm and 0.5 mm sieve openings, respectively. The work index of the material is
Correct : c
Similar Questions
A ball mill of 200 cm diameter grinds solid materials while operating with 10 cm size balls. If the same ball mill is used for wet grinding, charged with 20 cm...
In a feed milling plant, it has been observed that 80% of the feed passes through IS sieve 340 (3.25 mm opening) and 80% of the ground feed passes through IS si...
In grinding of black pepper, 80% feed passes through 6 mm screen, and 80% product passes through 0.5 mm screen. The gross energy required is 10 kW.h per ton of...