Agricultural Engineering > GATE 2018 > Size Reduction
In a feed milling plant, it has been observed that 80% of the feed passes through IS sieve 340 (3.25 mm opening) and 80% of the ground feed passes through IS sieve 40 (0.42 mm opening). The power requirement to crush the material with a feed rate of 3 ton h-1 is 6 kW. Power requirement to crush 2 ton h-1 of the same feed using the above system so that 80% of the ground feed pass through IS sieve 15 (opening 0.157 mm) is

Correct : 8

Similar Questions

A ball mill of 200 cm diameter grinds solid materials while operating with 10 cm size balls. If the same ball mill is used for wet grinding, charged with 20 cm...
#240 Fill in the Blanks
In a size reduction operation, the power required to crush 2 ton of feed material per hour is 7.2 kW. Eighty per cent of the feed and product material pass thro...
#254 MCQ
In grinding of black pepper, 80% feed passes through 6 mm screen, and 80% product passes through 0.5 mm screen. The gross energy required is 10 kW.h per ton of...