Agricultural Engineering > GATE 2018 > Biogas
A 2 m3 biogas plant is to be operated using cow-dung as feedstock. The cow-dung is mixed with water in proportion of 1:1 (by weight) to form a slurry of density 1090 kg m-3. The yield of biogas is 0.036 m3 kg-1 of cow-dung. If the hydraulic retention time is 40 days, volume of the digester of the biogas plant will be
Correct : 4.05
Similar Questions
The amount of biogas required to run a diesel engine is 0.65 m³ kW⁻¹ h⁻¹. The minimum size of the Deenbandhu model biogas plant in m³ required to run a 1 kW (br...
Constituents of the producer gas contributing to its heating value are
The untimely loss of life is a cause of serious global concern as thousands of people get killed ________ accidents every year while many other die ________ dis...