Agricultural Engineering > GATE 2015 > Weirs
A Cipolletti weir has the crest length of 1.2 m and a crest water level of 0.5 m. The average approach velocity of water in m s⁻¹ on the crest is
A
0.49
B
1.18
C
1.19
D
1.32

Correct : a