Agricultural Engineering > GATE 2014 > Terracing
Bench terraces are to be constructed on a 15% hill slope. The batter slope is 1:1 and vertical interval is 2.5 m. The earth work in cutting is equal to filling. The quantum of earthwork in m3 ha–1 will be
A
2656
B
2818
C
4248
D
5312

Correct : a