Agricultural Engineering > GATE 2014 > Terracing
Bench terraces are to be constructed on a 15% hill slope. The batter slope is 1:1 and vertical interval is 2.5 m. The earth work in cutting is equal to filling. The quantum of earthwork in m3 ha–1 will be
Correct : a
Similar Questions
It is proposed to develop bench terraces in an area having land slope of 10%. If the vertical interval between the bench terraces is 2.5 m and the batter slope...
If the width of bench terrace is W, drop D and existing land slope S; then for 150% batter slope, the drop D will be