Aerospace Engineering > GATE 2017 > Time and Work
1200 men and 500 women can build a bridge in 2 weeks. 900 men and 250 women will take 3 weeks to build the same bridge. How many men will be needed to build the bridge in one week?
A
3000
B
3300
C
3600
D
3900

Correct : c